1. When the straight seam steel pipe is hung, the wire rope is not allowed to be pulled diagonally to prevent the wire rope from falling out of the groove.

2. Pay attention during operation to ensure personnel and equipment.

3. Frequently check the switches on the front and back of the trolley, and whether the switch with the hook rising to a greater extent is sensitive.

4. Lubrication points such as straight seam steel pipe gears, sprockets, chains, and ropes should be refueled on schedule.

5. To operate the cantilever crane, closely cooperate with the hanging personnel and follow the hanging command.

6. The hook should be full of coils.

7. The wire rope should be replaced when 10% of the strands are broken.

8. Always check whether the hook lifting and holding brake are sensitive.

9. When the straight seam steel pipe is hoisted, the steel coil should be raised and lowered gently, and the operation should be stable, accurate, and light.